|
MEETING MINUTES
Yankee Rowe Community Advisory Board December 1, 1999
The eleventh meeting
of the Yankee Rowe Community Advisory Board(CAB) was held at the Charlemont
Inn, Charlemont Massachusetts on December 1, 1999. The meeting was called
to order by Vice Chairman Gail Cariddi at 7:07 PM.
CAB ATTENDEES
Gail Cariddi
Doris Lewis
Lenny Laffond
Nina Newington
Rick Williams
Ken Plumley
Anita Barker
Anne Skinner
Chuck Bellows
Bob Gallaghar
Jack Cable
Gail Cariddi introduced
Jack Cable as the newest CAB member. Jack will represent Heath.
The minutes of the
10/13/99 meeting were approved and accepted.
PRESENTATIONS
Rocky Marcello, General
Manager of Environmental Health and Safety
Dry Cask Fuel Storage Project Update
Rocky clarified that
Yankee's dry fuel storage facility is being built for Yankee Rowe's fuel
only. He said the spent fuel pool will not be dismantled until 2002 at
the earliest.
Len Trembley, Senior
Project Engineer, Dry Cask Licensing Update
Key Points:
- The plant ceased
operation in 1991, so fuel has been out of the
reactor for eight years
- $2 million is being
spent to design and license this system- A staff of 35 are on the
team to build dry cask storage- 2 years were spent getting NRC approval
- NAC has more transportation
experience than all other vendors- Yankee was very involved
and helped NAC with design of casks- Yankee's goal is to ship the fuel
as soon as possible
- Yankee has insisted
on all stainless steel with no coatings for internal fuel canisters
as some canister coatings have caused problems in the industry
- The storage casks
will be lined with three and one half inches of steel surrounded
by 21 inches of reinforced concrete- The casks will weigh 110 tons fully
loaded
- If option becomes available to ship fuel, Yankee will be ready- Handout
- Safely Stored and Ready For Transport was passed out-
Transportation testing has been completed in great detail
Anita Barker asked
if Palisade's casks were only for storage. Len said that was correct,
but Yankee is using a dual purpose system that prepares fuel for shipment
as well as storage.
Nina asked about
the crane that will move the fuel and Len told her that it had been updated
to a "single failure proof" criteria. Nina was concerned that
a crane remain if the fuel needed to be moved again. Len said the yard
area crane will be dismantled along with the spent fuel pool. Fuel will
need to be lifted again by portable cranes to go from storage to transport
cask.
Gail Cariddi asked what percent of the fuel has been in the pool eight
years. Len explained that all the fuel in the pool is at least eight years
old, with some dating back to the 1970s.
Joe McCumber, Dry Cask Construction Site Developments:
- Yankee will continue to update the CAB on dry cask construction
activities and fuel loading status
- There will be 16 casks. 15 will contain fuel assemblies and one will
contain other high-level waste (Reactor vessel internal
pieces)
- Construction of the cement storage pad will begin in the spring of 2000
and end in the fall of 2000
- Fuel inspection campaign planned for early 2000I- Fuel transfers to
dry cask planned for 2001
Contingency Plan:
- Spent fuel pool intact until 2002
- At least I year of dry cask operation before pool is dismantled- Contingency
plan to be developed
Q & A Session
Nina Newington raised
concerns about not having a spare canister available and the removal of
the spent fuel pool. Len Trembley said that the DOE is required to remove
any fuel, in the event of a faulty canister, to one of their facilities.
It was decided that the two subcommittees will meet in mid-January and
that the chairmen would let the members know when the meetings will be
held. Gail Cariddi announced that the full CAB would meet again in March
and members will be notified.
The meeting was adjourned at 8:32 PM.
A video of the meeting is available by calling Mandy Comai at 413-424-5498
or e-mailing a request to mcomai@together.net.
Respectfully submitted,
Doris Lewis,
Secretary
|