|
During the
early hours of Sunday, April 27, 1997, workers at the Yankee Rowe
plant prepared to open the plant gates to let the heart of the Yankee
Rowe plant, the reactor pressure vessel, begin the first phase of
an 1,100 mile journey through nine states that would bring the package
to its final resting place in South Carolina.
The reactor
vessel, which held the fuel that generated more than 33 billion
kilowatt-hours of electricity over 31 years, had been removed from
the plant's containment building last November. The 165 ton vessel
was placed inside a 3-inch thick, 100 ton steel container certified
by the NRC for transport. It was then injected with about 80 tons
of concrete and the lid was welded onto the container.
The package,
which weighed 365 tons including 20 tons of wire rope tie down equipment,
would be the last large component removed from the plant as part
of decommissioning.
The first phase
of the shipment involved the transport of the package from the plant
to the local rail spur at the Hoosac Tunnel in Florida, MA. Barnhart
Crane & Rigging of Memphis, TN had been hired to do the job,
and they were ready at 6 a.m. as planned.
As daylight
spread over the Deerfield River Valley and the media waited patiently
for pictures, the 365 ton package, escorted by State Police, began
the 6.5 mile trek at the Sherman Dam Bridge and then turned onto
River Road.
RPV
Shipment a Great Success!
Flanked by
Yankee personnel, it made its way slowly a little more than
one mile per hour into the town of Monroe where curious residents
were out on the sidewalks waiting to watch it pass by. Jane Grant,
Decommissioning Manager, walked ahead of the transporter handing
out commemorative hats to onlookers. Mort Fairtile of the Nuclear
Regulatory Commission joined Jane for part of the 6.5 mile walk,
as well as Peter Fowler of Yankee, who coordinated security provisions
for the shipment.
The transport
continued without incident through Monroe and Florida, MA arriving
at the rail spur ahead of schedule at 11:08 am. Over the next two
days, employees of Barnhart Crane & Rigging, Cianbro, Bartlett
Nuclear and Yankee removed the transporter tie downs and hydraulically
transferred and secured the package to a rail car.
The rail car,
which was leased from TransAlta Utilities Corporation of Alberta,
Canada, was chosen because it was designed to transport large, heavy
loads and has the ability to shift the load from side to side to
clear obstacles. The package would be shipped by dedicated train,
including an engine, two gondola cars, the rail car with the package,
two more gondola cars and a passenger car.
Although it
was not required to escort the shipment, Yankee decided to send
specific personnel with it to demonstrate and document the process
and to ensure Yankee's commitment to safety "from start to
finish." In addition, the shipment had received considerable
advance publicity from anti-nuclear activists and Yankee wanted
to be open about the process and provide the media with access to
information throughout the trip. It was also necessary for three
rail car operators to be available to shift the load if there were
any tight curves or obstacle
8 Days
8 Nights 9 States
Accompanying
the shipment were Leo Lessard, manager of the reactor vessel shipment
project, radiation specialists Rich Warnick and Chris Martel, Kelley
Smith, media and public relations representative, Lloyd Doige, Jess
Debnam and Ron Magnusson (the three rail car operators from TransAlta),
and Bob and Mary Bunch. Mary provided the crew with meals and Bob
maintained the passenger car. In addition, John Parker, engineer
for the Yankee Rowe Project, followed the train in a car. He didn't
have to worry about getting lost though because each rail company
provided a security escort for their respective section of the trip.
John followed the security vehicle and as a result was able to take
some good photographs of the train.
At 7:40 p.m.
on Tuesday, April 29, 1997, the train left the rail spur and entered
the Hoosac Tunnel amid waves and cheers from all who had worked
so hard to reach this milestone.
But the journey had just begun. The package would have to travel
almost 1,100 miles at speeds of 10 to 25 miles per hour and be transported
by five rail companies GTI, Canadian Pacific, Conrail, Norfolk
Southern and CSX. Traveling, except for the route between the Hoosac
Tunnel and Mechanicville, N.Y., would be done during the day with
the train held over at various train yards each evening. There would
also be delays. If train traffic was heavy, the package would be
pulled over to let faster trains through. The best estimate for
the trip was between 5 and 10 days.
The first leg
of the trip ended in the early morning hours at the Mohawk train
yard just outside of Mechanicville, NY. The next day brought the
train to Binghamton, NY where it was kept overnight. Thursday morning
the train left for Harrisburg, PA arriving later that day and staying
overnight before heading to Hagerstown, MD Friday morning. The train
was kept overnight in Hagerstown, then left Saturday morning for
Roanoke, VA. After an overnight stay in Roanoke, it was on to North
Carolina. The train stayed in Linwood, NC Sunday night and left
Monday morning for Spartanburg, SC. Tuesday brought the train from
Spartanburg, SC to Columbia, SC where it spent its last evening
before heading to its final destination. Yankee president, Andy
Kadak, joined the train in Clinton, SC and stayed with it until
it reached Barnwell.
At 5:03 p.m.
on Wednesday, May 7, 1997 after eight days on the rails
the train pulled into Barnwell, S.C.
Other than
a few cows that needed to be herded away from the tracks, and less
than five protesters, the trip went smoothly and without incidence.
The train did receive a lot of media attention along the way, with
news helicopters filming it from the air and cameramen, news photographers
and reporters tracking it. They were also waiting for the train
in Barnwell, SC where they reported that the Yankee Rowe package
would bring $1 million to South Carolina educational funds.
Journey
Ends Safely in South Carolina
Over the next
several days, the package was transferred from the rail car to a
road transporter. On May 13, 1997, the package was moved from the
rail spur to the Chem-Nuclear Low-Level Radioactive Waste Disposal
Facility and placed inside a trench where it will eventually be
buried.
Although the
shipment took only a few days, it took more than a year of meticulous
planning and attention to detail to prepare for it. This shipment,
like Yankee's more than 30 years of operation and decommissioning
program, was safe from start to finish.
|
 |
|
The
reactor vessel package makes its way over the Sherman Dam
Bridge shortly after it began its journey from the Yankee
Rowe plant to the Hoosac Tunnel rail spur.
Photo by Ron Waterman
|
 |
|
The
reactor vessel package on River Road headed for the Hoosac
Tunnel.
Photo by Ron Waterman
|
 |
|
The
RPV Shipment Team gathers in front of the package before it
leaves the Hoosac Tunnel
Photo
by Ron Waterman
|
 |
|
With
a GTI engine ready to go, the dedicated train awaits departure
from the rail spur in Florida, MA.
Photo by Ron Waterman
|
 |
|
The
dedicated train carrying the RPV package enters the Hoosac
Tunnel on the first leg of its journey to SC.
Photo by
Ron Waterman
|
 |
|
On
May 13, 1997, the reactor vessel package was moved to Chem-Nuclear's
Low-Level Waste Disposal Facility and placed inside a trench
next to the Salem nuclear plant steam generators.
Photo
by Ced Child
|
|