General Information
  • ownership
  • directions
  • press room
  • links

    Site Closure

    Decommissioning
  • building demolition
  • updates
  • large comp removal/ship
  • other decomm projects

    Fuel Storage
  • federal responsibility
  • fuel transportation

    License Termination
  • radiation
  • background radiation

    Community Board
  • members
  • charter
  • meeting minutes

    Regulatory Reports
  • NRC
  • Other
  •  

    Although many large components were removed and shipped from the Yankee Rowe plant as part of decommissioning, the largest was the reactor vessel. All of the large component removal projects involved extensive engineering, planning and licensing efforts. We have chosen the reactor vessel removal and shipment to help illustrate these removal and shipment projects.

    Reactor vessel removal
    Reactor vessel shipment


    Yankee Removes Reactor Vessel

    The reactor vessel at the Yankee Rowe Nuclear Power Station was safely and successfully removed from containment on Wednesday, November 20, 1996, and placed in a specially designed, NRC-approved shipping container. The reactor vessel was stored in the container on-site until April 1997 when it was shipped to a low-level waste disposal facility in Barnwell, South Carolina.

    Yankee Rowe's reactor vessel is suspended by a crane inside the containment sphere prior to being lowered through an equipment hatch into a shipping container (see other photo this page). The 165-ton vessel housed the nuclear fuel that produced more than 33 billion kilowatts over a 31-year period.

     
    The removal procedure began at 8:45 a.m. and was completed at 11:25 a.m. Prior to the removal, the 90-ton steel shipping container was moved into an upright position underneath the containment sphere. The opening of the shipping container was matched to the opening of the equipment hatch on the underside of the containment sphere. Using a large crane inside the containment sphere, the 165-ton reactor vessel was lifted and then lowered through the containment equipment hatch into the shipping container.

    Workers then injected about 80 tons of concrete into the reactor vessel and the spaces between the vesel and its shipping container, and permanently welded on the container lid.

     
    The 90-ton steel shipping container sits upright underneath the containment building ready to receive the vessel.
    Photo by Ron Waterman

    The reactor vessel, which once held the fuel used to generate electricity, is approximately 27 feet long and 12 feet at its widest point. The vessel is made of carbon steel with 8-inch thick walls. The shipping container is 28 feet long and 13 feet in diameter.

    The removal and shipping procedures for thereactor vessel were similar to the procedures used for the successful removal and shipment of Yankee's four steam generators in late 1993.

    Yankee expects to complete this phase of the decommissioning process by the end of 1997, and has made a commitment to return the site to a green field condition.

    Yankee cannot return the entire site to a green field until the U.S. government provides either a centralized storage facility or permanent repository for Yankee's 533 used fuel assemblies.

    Yankee ships reactor vessel

    During the early hours of Sunday, April 27, 1997, workers at the Yankee Rowe plant prepared to open the plant gates to let the heart of the Yankee Rowe plant, the reactor pressure vessel, begin the first phase of an 1,100 mile journey through nine states that would bring the package to its final resting place in South Carolina.

    The reactor vessel, which held the fuel that generated more than 33 billion kilowatt-hours of electricity over 31 years, had been removed from the plant's containment building last November. The 165 ton vessel was placed inside a 3-inch thick, 100 ton steel container certified by the NRC for transport. It was then injected with about 80 tons of concrete and the lid was welded onto the container.

    The package, which weighed 365 tons including 20 tons of wire rope tie down equipment, would be the last large component removed from the plant as part of decommissioning.

    The first phase of the shipment involved the transport of the package from the plant to the local rail spur at the Hoosac Tunnel in Florida, MA. Barnhart Crane & Rigging of Memphis, TN had been hired to do the job, and they were ready at 6 a.m. — as planned.

    As daylight spread over the Deerfield River Valley and the media waited patiently for pictures, the 365 ton package, escorted by State Police, began the 6.5 mile trek at the Sherman Dam Bridge and then turned onto River Road.

    RPV Shipment a Great Success!

    Flanked by Yankee personnel, it made its way slowly — a little more than one mile per hour — into the town of Monroe where curious residents were out on the sidewalks waiting to watch it pass by. Jane Grant, Decommissioning Manager, walked ahead of the transporter handing out commemorative hats to onlookers. Mort Fairtile of the Nuclear Regulatory Commission joined Jane for part of the 6.5 mile walk, as well as Peter Fowler of Yankee, who coordinated security provisions for the shipment.

    The transport continued without incident through Monroe and Florida, MA arriving at the rail spur ahead of schedule at 11:08 am. Over the next two days, employees of Barnhart Crane & Rigging, Cianbro, Bartlett Nuclear and Yankee removed the transporter tie downs and hydraulically transferred and secured the package to a rail car.

    The rail car, which was leased from TransAlta Utilities Corporation of Alberta, Canada, was chosen because it was designed to transport large, heavy loads and has the ability to shift the load from side to side to clear obstacles. The package would be shipped by dedicated train, including an engine, two gondola cars, the rail car with the package, two more gondola cars and a passenger car.

    Although it was not required to escort the shipment, Yankee decided to send specific personnel with it to demonstrate and document the process and to ensure Yankee's commitment to safety "from start to finish." In addition, the shipment had received considerable advance publicity from anti-nuclear activists and Yankee wanted to be open about the process and provide the media with access to information throughout the trip. It was also necessary for three rail car operators to be available to shift the load if there were any tight curves or obstacle

    8 Days — 8 Nights — 9 States

    Accompanying the shipment were Leo Lessard, manager of the reactor vessel shipment project, radiation specialists Rich Warnick and Chris Martel, Kelley Smith, media and public relations representative, Lloyd Doige, Jess Debnam and Ron Magnusson (the three rail car operators from TransAlta), and Bob and Mary Bunch. Mary provided the crew with meals and Bob maintained the passenger car. In addition, John Parker, engineer for the Yankee Rowe Project, followed the train in a car. He didn't have to worry about getting lost though because each rail company provided a security escort for their respective section of the trip. John followed the security vehicle and as a result was able to take some good photographs of the train.

    At 7:40 p.m. on Tuesday, April 29, 1997, the train left the rail spur and entered the Hoosac Tunnel amid waves and cheers from all who had worked so hard to reach this milestone.

    But the journey had just begun. The package would have to travel almost 1,100 miles at speeds of 10 to 25 miles per hour and be transported by five rail companies — GTI, Canadian Pacific, Conrail, Norfolk Southern and CSX. Traveling, except for the route between the Hoosac Tunnel and Mechanicville, N.Y., would be done during the day with the train held over at various train yards each evening. There would also be delays. If train traffic was heavy, the package would be pulled over to let faster trains through. The best estimate for the trip was between 5 and 10 days.

    The first leg of the trip ended in the early morning hours at the Mohawk train yard just outside of Mechanicville, NY. The next day brought the train to Binghamton, NY where it was kept overnight. Thursday morning the train left for Harrisburg, PA arriving later that day and staying overnight before heading to Hagerstown, MD Friday morning. The train was kept overnight in Hagerstown, then left Saturday morning for Roanoke, VA. After an overnight stay in Roanoke, it was on to North Carolina. The train stayed in Linwood, NC Sunday night and left Monday morning for Spartanburg, SC. Tuesday brought the train from Spartanburg, SC to Columbia, SC where it spent its last evening before heading to its final destination. Yankee president, Andy Kadak, joined the train in Clinton, SC and stayed with it until it reached Barnwell.

    At 5:03 p.m. on Wednesday, May 7, 1997 — after eight days on the rails — the train pulled into Barnwell, S.C.

    Other than a few cows that needed to be herded away from the tracks, and less than five protesters, the trip went smoothly and without incidence. The train did receive a lot of media attention along the way, with news helicopters filming it from the air and cameramen, news photographers and reporters tracking it. They were also waiting for the train in Barnwell, SC where they reported that the Yankee Rowe package would bring $1 million to South Carolina educational funds.

    Journey Ends Safely in South Carolina

    Over the next several days, the package was transferred from the rail car to a road transporter. On May 13, 1997, the package was moved from the rail spur to the Chem-Nuclear Low-Level Radioactive Waste Disposal Facility and placed inside a trench where it will eventually be buried.

    Although the shipment took only a few days, it took more than a year of meticulous planning and attention to detail to prepare for it. This shipment, like Yankee's more than 30 years of operation and decommissioning program, was safe from start to finish.

    The reactor vessel package makes its way over the Sherman Dam Bridge shortly after it began its journey from the Yankee Rowe plant to the Hoosac Tunnel rail spur.

    Photo by Ron Waterman

     

    The reactor vessel package on River Road headed for the Hoosac Tunnel.

    Photo by Ron Waterman

     

     

    The RPV Shipment Team gathers in front of the package before it leaves the Hoosac Tunnel

    Photo by Ron Waterman

     

     

    With a GTI engine ready to go, the dedicated train awaits departure from the rail spur in Florida, MA.

    Photo by Ron Waterman

     

     

    The dedicated train carrying the RPV package enters the Hoosac Tunnel on the first leg of its journey to SC.

    Photo by
    Ron Waterman

     

     

    On May 13, 1997, the reactor vessel package was moved to Chem-Nuclear's Low-Level Waste Disposal Facility and placed inside a trench next to the Salem nuclear plant steam generators.

    Photo by Ced Child